Observatory
Observatory Project Update
The Thunder Bay Centre is pleased to be in partnership with Fort William Historical Park and the future installation of the David Thompson Observatory. The 15 foot observatory dome will house a world class 20″ telescope, that will deliver great views of all the gems of the universe. Dome construction has begun!!
January 2012
January 8 – After being cloudy all day, we had a brief clear patch between 5 and 8 to get some serious work done. The finder scope was remounted on the main scope, and it was aligned with the telescopes. The 20″ Planewave mirror was finally revealed today, a beauty it was. We used Jupiter as the target to align everything to, but for some reason we couldn’t get the telescope to track when we were doing this, but we got it pretty close. We had also planned on using the Ronchi tester to ensure that the secondary mirror was at the right spacing from the primary, however we thought that we better figure out the tracking first, and play a bit more with the software that controls the telescope. Turned out this would take us the rest of the evening. We started using the software to try and “goto” different stars, but every time we tried one, the scope seemed to have a mind of it’s own and went off in a way different direction. After scratching our heads and going through the software settings a number of times – we finally came upon the problem. We had the RA motor plugs in the DEC ports, and the DEC plugs in the RA ports. DUH!! Well it was good that we caught this early in the game! Back to home position and lets start over again…slew to Vega in the west …and it actually went the right way….and landed to within 2-3 degrees. A quick adjustment and sync, and we were off to Deneb..bang – right there! We went to a few more stars, and had to sometimes use the scope handpad to adjust, but in the end we had a 7 point star model, and the telescope was tracking. Using this small amount of data, the computer was able to tell us that we were 2 degrees to the left and one degree down from being polar aligned. We adjusted the scope in Azimuth, but lacked the proper wrench to do the Altitude adjustment. By this point we were all a little chilly, and the wisps of clouds started to come in, so we decided to call it a night. We put all the caps back on everything, parked the telescope, and saved the model mount that we had just created so we can call it up the next time we go out to do more work. Next steps – refine polar alignment, get The SkyX working with the SciTech telescope program, and test out the mallincam.
Mount/Scope Installation – Late December
December 28 – Work in the last few weeks has been limited, here is a quick list of what has been done. Secondary scope and finder scope were mounted to primary, control cables were run through conduit to computer, foam matting was installed on concrete floor, red rope light was installed around bottom of dome, and software installation was completed. Now the fun part – trying to get the PC to talk to the mount. That’s the next challenge for the new year.
Mount/Scope Installation – Early December
December 5 – THE SCOPE IS UP!! Today the scope was delivered to site, uncrated and lifted up into it’s final resting place. It was kind of funny when we tightened the dovetail plate. Some people just didn’t think they should let go! It is a pretty daunting thought of that thing coming down on you. Once we got over that fear, the scope was given a primary balancing, and was wired up with power. We managed to get it working by hand control (once we figured out we plugged the DEC and RA axis leads into the wrong plugs), and the motors were very very quiet for a beast this size. Also did a bit more software installation, with a little bit more to go. It is a very impressive looking scope, lets hope it serves the public well for many years to come!
December 3 – Another successful day, today the pier was oriented and leveled, the mount and counterweights got installed, the observatory computer got moved out to the observatory, the dome controller was hooked up to the computer via serial port, the dome and shutter were trained, and remote communications with the control room PC was established. The new telescope was also viewed (in it’s crate) for the first time!
Dome Construction Day 3 – Dec 2, 2011
Today the dome was finished!! The dome is operational from the hand control inside of it. There are a few little quirks but nothing that can’t get ironed out in the future. Tomorrow the plan is to get the dome working through the computer and using the remote computer to operate it.
Dome Construction Day 2 – Dec. 1, 2011
DOME CONSTRUCTION DAY 1 – NOV 30, 2011
Mid-November 2011 Update
It has been a flurry of activity at the construction site over the last few weeks. Both the observing pad and the dome pad/pier are complete, and work has begun on the classroom/control room building. Arrangements have been made for the dome manufacturer to come up and assemble the dome at the end of the month.
Early November 2011 Update
Excavation for the new pier has begun! The goal before the snow flies is to have the concrete pier, dome pad, observing pad complete, as well as to get the dome built and functional. It is our understanding that the concrete pad for the classroom will also be poured this fall.
September 2011 Update
Demolition of the existing building has taken place, and tenders are currently out for the construction of the concrete pads.
August 2011 Update
The environmental assessment has finished, engineering drawings are near to completion, and tenders should shortly be going out for demolition, and concrete pad construction.
July 2011 Update
All of the equipment and the dome are on-site, in storage at FWHP. Because the project is on government property, it is subject to an Environmental Assessment, which is a process that has been ongoing. This has been completed, and needs to be posted publicly for a month.





































